One project, four numbers
A project runs from Monday, June 8 to Friday, August 21, 2026:
| Measure | Value | Use it for |
| Days between the dates | 74 | Elapsed time in a status report |
| Dates covered, both ends included | 75 | Rental or license periods that charge per day |
| Weekdays | 55 | Capacity for a UK team, which has no bank holiday in this range |
| US working days | 53 | Capacity for a US team, after Juneteenth and the July 3 Independence Day holiday |
Put both the calendar span and the working-day count in the plan. "74 days" sounds like more time than "53 working days," and both are true.
Adding working days to a start date
"10 working days from Monday, June 8, 2026" usually means counting from the next day: June 9 is day 1, and day 10 is Monday, June 22. In a spreadsheet, =WORKDAY(A2, 10, H2:H12) gives the same date, with holidays listed in H2:H12.
Counting back from a launch date
A launch is set for Friday, December 4, 2026, and testing needs 15 US working days that finish on Thursday, December 3. Counting back and skipping weekends and Thanksgiving, testing has to start on Thursday, November 12. Forgetting Thanksgiving gives November 13, which leaves the team a day short.
In a spreadsheet, =WORKDAY(A2, -15, H2:H12) counts backward from the day after the last testing day.
Sprints and holidays
A two-week sprint from Monday to Friday of the following week has 10 working days. The sprint from June 15 to June 26, 2026 has 9 for a US team because of Juneteenth on Friday, June 19. Adjust the sprint's commitment, not just its dates.
Quarters are not equal
Q4 2026, October 1 to December 31, has 66 weekdays. A US team loses Columbus Day, Veterans Day, Thanksgiving, and Christmas, leaving 62. A team in England and Wales loses Christmas Day and the Boxing Day substitute, leaving 64. The US and UK pages list working days for every month to 2030.
End dates: inclusive or exclusive
"The project ends August 21" normally means work happens on August 21. Some tools and file formats store the end as the first day after the period, August 22. Mixing the two styles makes every duration off by one. Pick one style for the plan and label it.
What working-day counts leave out
- Personal leave and part-time schedules. Multiply working days by each person's availability.
- Company shutdowns, such as the week between Christmas and New Year.
- Teams in several countries. Count each location with its own holidays.